What Task Intervals Should be Used?
MaintSmart contains a unique feature that actually
performs reliability analysis on an equipment item based on the item's
failure cause. In this case the Fryer #1 had a
MTBF (average time between failures) of approximately 45
days for the break down cause 100 Out of Time. Now that
you know how often the Fryer #1 can be expected to fail because it out of
time you may take the appropriate steps to prevent this failure
cause. There are already 3 assigned tasks meant to prevent this
break down cause however there completion Interval is 60
days. To prevent this failure the maintenance manager should set these PM
tasks to be performed at 45 day or shorter
intervals. Fortunately this is very simple to do from this
screen by simply right mouse-clicking the grid row containing the record and entering
the new interval time. You may also add tasks to the PM list for this equipment item from
this screen .
Remember the tasks seen on this reliability
analysis screen are actually part of an existing PM task list for this
equipment item that has been previously set up. This powerful feature is
usful for removing unneeded tasks from a PM task list as well.
MaintSmart WILL make your maintenance operation more
efficient!